Engineer / Project Engineer, EDYCE CORP, varios
START Date:
April, 2001
END Date:
November, 2005 I was Responsible for the administration and coordination of the following projects:
- Minera Escondida Silos de Transferencia, Fluor
- Conveyor Belts Dry, Codelco Chile
- Escondida Phase IV, BHP Billiton
- Boiler Recovery from Botnia Pulp Plant, Metsä-Botnia
- Plant of Pulp New Aldea, Celulosa Arauco
- New port for Abastible gasline, Belfi
- Expansion of Smelter Plant ILO, Isasmelt - Southern Peru Copper Corporation
- Airport “A. Merino Benítez”, Ministerio de Obras Publicas – MOP
- Metro 4th Line Project, Metro Chile
Experience Hours (Planning & Scheduling):
2000
Experience Hours (Cost Management):
4000
Experience Hours (Forensic Analysis):
2000 - Company:
- Industry:
- Job Role:
- Project: