Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Building Services M&E MEP Senior Planner, N G Bailey & Co, HMP Shotts New Build Prison Facility £50m

START Date: 
July, 2010
END Date: 
July, 2011

M&E Planning Manager HMP Prison New build £50m, responsible for all M&E planning and coordination with Carillion Main Contractor

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Forensic Analysis): 
250