Consultant Planner, Thanglong JOC, HST/HSD Development Project
START Date:
September, 2011
END Date:
December, 2011 HST/HSD Development Project (Offshore Oil & Gas) 2 x WHPs, in-field pipelines, tie-ins to existing production system, drilling campaign. Delivered industry standard work package element level resource-loaded project baseline schedule for Decision Support Package/ FID. Mentor/ guide contractor/ client planners.