Turnaround Planner, Izandla Engineering (Seconded to Aveng Grinaker LTA), Chevron Turnaround 2015
START Date:
October, 2014
END Date:
March, 2015 - Review, Develop, Plan, Maintain & Track the Piping schedule using Primavera P6
- Monitor the Work List for changes and scope growth.
- Create and manage activity logic
- Develop, update and manage resource Histograms and S-Curves
- Maintain and control the KPI for all contractual disciplines
- Track and Report on Workshop Pre-Fabrication and report on any issues
- Track Materials and report on shortages and delays for long lead items.
- Perform Daily updates and reports with S-Curves for progress meetings with Stakeholders.
- Interfaced with Operations, Client, Subcontractors and Suppliers to discuss impact of work and resolution of problems
- Lead weekly Construction Meetings.
- Compile daily updates for supervisors indicating critical path, progress and slippage (also reasons).
- Monitor Potential scheduling problems and report to senior management
- Monitor progress and update the schedule accordingly
- Participate in progress meetings with the Client