Site Planner, Nexen Petroleum UK Ltd, Golden Eagle

START Date: 
May, 2012
END Date: 
April, 2014

Based on site at Jebel Ali, Dubai, UAE on the construction and commissioning of 2 topsides. Responsibilities include maintenance of the construction plans, development and maintenance of the commissioning plans and reports using Primavera P6.