Project Planner, Buckingham Group Contracting Ltd, IBC-Demolition/strip out works and MUA (Copperbox) Queen Elizabeth Olympic Park-Transformation Works

START Date: 
March, 2013
END Date: 
October, 2013
  • Development of Tender programme into an accepted/construction programme.
  • Update/Revise programme with all PMI, Change requests, Compenstation Events, Early Warnings etc
  • Cost/Resource loaded programme
  • Liasing with senior amangement and memebers of project team with regards to programme control and management.
Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200