Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Project controls specialist/Lead scheduler, Exxon - BCIT, Pilot Plant constructions

START Date: 
February, 1994
END Date: 
February, 1998

►     Exxon - Basic Chemical Intermediates Technology, Baytown, TX, 1994 to 1998

Project Manager. The scope was to build and operate in-house pilot plants. The intent was to cover a wide range of process applications and chemical products in regard to demonstrating anticipated operations, integrating unit process in real time, identifying potential problems, confirming feed and utility needs, and proving product quality and generating market sample. Had oversight/management responsibility in design, fabrication, construction, and startup. Representative pilot plants: Acid Acetic, Vinyl Acetate Monomer, Vinyl Choride monomer, Olefins -alpha-olefins Plant, Polyethylene Plant.