Site Engineer, Jyothi Engineering, A P Rayon-Expansion of Pulp production from 300 TPD to 350TPD

START Date: 
January, 1995
END Date: 
March, 1999

·         Actively participated in Mechanical installations and fabrication of steel & carbon steel piping for Pump Mill & Clo2 Plant.

·         Handled the erection of process equipments like drum washer, gas free rotator vacuum, tank ages, and chimney of Soda Recovery Boiler etc.

·         Inspection of materials and Storage at site. Auditing, verification and follow up of corrective actions.

·         Document Control, Preparation of Check lists. Preparation of Operation and Maintenance manuals, etc.

Prepare Trend and forecast reports, Weekly and Monthly reports for Management.