Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Construction Project Planner / Senior Planner, Besix Orascom JV, Giza North 1500MW Combined Cycle, Power Plant

START Date: 
February, 2009

1)    Orascom Construction OCI- BESIX

Since Feb 2009 (Current Employment)

Senior Planning & Scheduling Engineer

A.   Giza North 1500MW Combined Cycle, Power Plant, Contract Value $ 70.2 Million + EGP 562.7 Million.

Ø  Issue the tender schedule of the project; assign major resources histogram using Bill of Quantity in coordination with Quantity Surveying and tender departments.

Ø  Preparation of the project cash flow to be submitted to tender department.

Ø  Prepare Schedule Narrative to assist tender department in preparing the method of statement for the project in tender stage.

Ø  Assist in the preparation of project file schedule after submission of all the required data to tender department and prepare presentation for the project as required.

Ø  Prepare and issue the base line schedule and assign the project resources in details. 

Ø  Collect data from owner Bill of Quantity to issue the cash in to be used in forecasting the income of the project

Ø  Monitor the progress of the project activities according to project/department requirements to verify that the updated schedule comply with the approved base line schedule and highlight critical issues and provide analysis to Direct Manager.

Ø  Prepare daily, weekly, and monthly progress reports about the project and provide input to Direct Manager according to project/department requirements.

Ø  Provide data regarding the project schedule to cost control engineers, and finance department to be used in preparing financial statement, cost plan, billing plan and cash out reports.

Ø  Prepare and issue the “Contract Cash flow WBS” in Primavera schedule of the project.

Ø  Prepare and issue Productivity reports of items and Buildings of the project.

Ø  Track and analyze procurement cycle for project.