Project Controls Engineer, Exxonmobil - Mobil Nigeria Unlimited, Qua Iboe Power Project (QIPP)
START Date:
May, 2010 Mobil Producing Nigeria Unlimited April 2011 till date
Mobil House, 1 Lekki Expressway, Victoria Island Lagos.
Department: Nigerian Project Organisation (NPO)
Qua Iboe Power Project (QIPP)
Position: Project Controls Engineer
• Developed and resource loaded project detailed schedule with close to 3000 individual activities using Primavera Project Planner (P3) (Scheduling Tool)
• Participated in the development of Estimate Confidence Package (ECP) Template for the Project Controls Engineering function
• Developed Schedule Template for ECP using GanttBeDone which is MS Excel based programme that makes use of macros.
• Monthly progress measurement using the agreed percentage weight attached to each milestone for each activity/ deliverable
• Stewardship and presentation of monthly project status, plan, actual and forecast reports
• A key contributor to the development of 2 Lump Sum EPC Invitation to Tenders. Developed Exhibit D (Company Schedule) Attachment, established key milestones from the Company’s detailed schedule, defined the intent of each milestone, the actions required to achieve that particular milestone.
• Developed Company’s proposed cash flow during project execution to ensure perfect cash flow to contractor and smooth execution of the project
• Developed Project’s Management of Change Procedure for execution of the project using standard company template
• Participated in the development and revision of the project Cost Estimate
• Participated in the Project’s safety activities like Monthly Project Safety Meeting, Weekly Safety Presentation, Management Safety Walkthrough, U-See, U-Act