Field Control Coordinator, Snamprogetti S.p.A., Ruwais Refinery Expansion Project – Condensate Processing, Utilities & Off-Site

START Date: 
August, 1998
END Date: 
December, 1999

Project: Refinery Expansion Project – Condensate Processing, Utilities & Off-Site

Location: Ruwais, UNITED ARAB EMIRATES

Recruited during the installation phase of the Ruwais Refinery Expansion Project which covers the construction of two parallel trains for the distillation of condensate from Onshore Gas Development and Asab Gas Development Projects. The total plant capacity after expansion becomes 280,000 barrels/day of condensate processing with associated downstream facilities such as naphtha stabilization, kerosene sweetening and offsite facilities including an additional tank farm comprising 23 large tanks.