Site Planner, Siemens, Singapore Jurong Cogeneration Project, ExxonMobil.
START Date:
September, 2015
END Date:
March, 2016 Sep 2015 – Mar 2016 AMIDA GLOBAL PTE LTD.
Seconded to SIEMENS, Batam Fabrication Yard as SITE PLANNER for Singapore Jurong Cogeneration Project, ExxonMobil.
The scope of works is a substation building with aprox weight 665 MT
Major E&I equipments inside the building are Gas Insulated Switchgear, switchgear, transformers, and overhead bridge crane.
• Generate progress monitoring report in þ basis, updating the fabrication schedule and highlighted in 2 weeks look ahead schedule and presented in weekly team meeting with client representative.
• Liase with construction team, subcontrators, procurement and engineering to gather all information, escalate any stopper issues or critical activities founded out from schedule analysis.
• Validating progress status report from subcontrators.
• Prepare and maintain the construction progress S-curves and man power histogram.