Manager Planning, NESCOM, Research Projects
START Date:
January, 2001
END Date:
July, 2008 - Responsible for planning of projects from level I to IV.
- Responsible for implementation of Level IV plan at site.
- Responsible for development of plant-wide master schedule including integration of engineering, procurement, maintenance, shutdown, and new construction schedules including critical path analysis using Primavera P3.
- Prepare, implement and monitor the Work Breakdown Structure (WBS) for control and integrity.
- Development and baseline management of multiple project schedules.
- Development of layouts and reports based on client and project team reporting requirements.
- Attend project/management meetings as required.
- Coordinate monthly project schedule and manpower update meetings and the distribution of reports in a timely manner.
- Conduct analysis of projects to highlight and identify specific problem areas.
- Retain historical information form cost impact analysis for future work.
- Assist in the development of template schedules.
- Monitoring project as per scheduled and budgeted cost.
- Performing all tasks related to cost/schedule of design and construction as well as provide schedule status and updates.
- Providing forecasts, assisting with estimating changes, and providing claims analysis.
- Develop manpower curves for production optimization.
- Implement Work Breakdown Structure ensuring no trade overlap.
- Manage resources and monitor equipment availability.
- Invoice the client based on Earned Value.
- Input daily engineering design submissions into master schedule ensuring construction scheduled had approved design drawings.
- Coordinated with contractors to generate 3 week look ahead schedules.