Planner, Hyder Consulting, Crossrail

START Date: 
October, 2012
END Date: 
March, 2013

I developed Hyder's design programme, with regular meetings with the contractor to determine the critical tasks.

I then imported all other design disiplines programmes to produce an integrated programme for the delivery of a bid programme.

Hyder won the tender.