Planning Engineer, Saudi Pan Kingdom - Sapac, Trauma Care Center, King Abullaziz Medical City, Riyadh

START Date: 
May, 2009
END Date: 
June, 2010

 

     * From 23-05-2009 till 22 – 06 - 2011 I am working in “SAUDI PAN KINGDOM – SAPAC –“

  On Planning DPT as Planning Engineer.

From 23-05-2009 till 27-06-2010:-

 I were in charge of re-planning & monitoring TRAUMA CARE CENTER “200 beds”, KING ABDUL AZIZ MEDICAL CITY – RIYADH - SAUDI ARABIA.

 I were responsible for:-

1-           Preparing daily report & weekly report about work progress in the project.

2-           Purchasing orders follow up with the purchasing DPT in the company & make weekly report about it.

3-           Preparing weekly look ahead for every responsible engineer.

 

I have participated in quantity surveying works for:-

1- Site Works “Excavation & backfilling works, Landscaping works, paving &

Surfacing works& road paving works.”

2- Concrete works.

3- Masonry Works.

4- Metal Works.

5- Insulation works.

6- Doors & Windows & preparing doors schedule.

7- Finishing works “Plastering, Flooring, Ceramics, Painting, Marble, and Gypsum Board (partitions & Ceilings), Acoustic Ceilings & wallpaper works”.