Senior Project Engineer, Kiska Construction, Maintenance 56 Bridges - D261778

START Date: 
January, 2001
END Date: 
October, 2018
Oswaldo Manangon, 

 

Project Assignment:                Senior Project Engineer - Kiska Construction

 Years of Experience:               With This Firm:  9.5                With Other Firms: 22  

    Education:                           B.S. inCivil Engineering, Polytechnic School Army Corps (ESPE), Quito, Ecuador, 1979                             .                      

 

    Active Registration:            30 HR OSHA Course on construction Safety and Health (29 CFR 1926), Joint Labor and Management Safety and Health Committees

                                                Fall Protection and New Steel Erection

 

Mr. Manangon is a experienced person of construction industry with almost 31 years of hands on knowledge in BidPreparation, Field Supervision and Contract Administration. He is familiar with OSHA requirements. Currently he is the Project Engineer on the Robert Moses Causeway Project

Computer literate and knowledgeable in construction related programs such as Expedition-Contract Manager, Primavera Project Planner (P3), Project Manager P6 Advance, Suretrack, Microsoft Project, Excel, Access, AutoCAD, Micro Station, HCSS and National Estimator. 

 

Some of the projects he was involved can be listed as:

 

Robert Moses Causeway Rehabilitation NYSDOT D261090-New York, New York

Responsible for field survey operation; coordination and control of all activities of topside work: basically hydrodemolition and overlay concrete placement. Daily control of labor crews and sub-contractors forces; log and cost proposals change orders; preparation of construction schedule work and tracking schedule progress; labor budget control coordination and preparation of quantities for monthly requisition. Total construction value of 35 million dollars

 

Reconstruction of High Line – Section I-Site Preparation Project  and Landscaping- New York, NY

Responsible for field survey of prefabricated planks, drainage and civil work,  checking of shop drawings for accuracy, preparation of sketches drawings for temporary work, coordination of labor crews and sub-contractors forces, and preparation of quantities for monthly requisition and change orders and preparation of construction schedule work and tracking schedule progress and evaluating project performance. Total construction value of 30 million dollars

 

Rehabilitation of Culver Line Viaduct– Brooklyn, NY

Responsible for field survey of steel work, checking of shop drawings for accuracy, coordination of labor crews and sub-contractors forces, and preparation of quantities for monthly requisition and change orders Total construction value of 14 million dollars

 

Rehabilitation of Grand St. Station - Flushing, NY

Responsibilities included direct supervision of labor trades job, coordination and scheduling, safety plan preparation and conducted safety meetings for the safety performance of the work

 

Highway Guaranda - Bilován – Balzapamba – Ecuador

Worked as the Coordinator of Highway Projects for the Ecuador Dept. of Planning. Responsibilities included cost estimating, bid documents, procurement of materials and equipment, subcontractor scheduling and coordination, job schedules, shop drawings and approvals, projects meetings. Technical Representative with State and Private Entities.

Experience Hours (Planning & Scheduling): 
30000
Experience Hours (Cost Management): 
25000
Experience Hours (Forensic Analysis): 
300