Claims Specialist, NORTH LUZON RAILWAY CORPORATION, North Luzon Railway Project Section I Phase I
Date : December 11, 2008 to Present
Employer : NORTH LUZON RAILWAY CORPORATION
Position : Claims Specialist
Project : PROJECT MANAGEMENT OFFICE
NORTH LUZON RAILWAY PROJECT
PHASE I - CALOOCAN CITY TO CLARK PAMPANGA (82 Km.)
( USD 1.3 B)
Duties : Responsible in the review, evaluation and management of all claims and request of
the Contractor for the cost increases, variations and time extensions among others,
and their conformity with the provisions of contracts;
Monitor the progress of all eligible claims as it passes through different
Departments/units to ensure timely action on such claims and ensure that
documentations are complete;
Monitor/facilitate processing of progress billings and accomplishments
Formulate and /or improve guidelines and procedures in the processing of various
claims to conform to contract provisions;
Analyze the impact of any claims and changes to the scope of the contracts as they
affect project cost and schedule;
Maintain and update unit cost analysis of all pay items and assess the impact of
any increase/decrease to the cost of the project as necessary and to future claims
Receives all daily activity reports of works engineering; evaluates and tracks in
conformance with contracts requirements.
Receives all requests for payment of progress billings, variation/extra work orders, time
extension, work suspension; checks compliance with document requirements for all
requests; reviews and expedites the processing of requests for recommendation to the
Project Manager.
Reviews contractual issues and recommends resolutions to the Construction Manager;
prepares Contract Variance reports and submits to the Project Manager.
Reviews construction methodologies and work/job orders; recommends approval as per
compliance with the contract requirements and government regulations.
Performs other functions that may be assigned from time to time.
Date : June 1, 2005 to August 31, 2008
Employer : MITSUBISHI HEAVY INDUSTRIES LTD. / SUMITOMO
CORPORATION/COMMBUILDERS & TECHNOLOGY PHILS.
Position : Scheduler / Cost Controller
Project : DESIGN AND CONSTRUCTION OF CAPACITY EXPANSION PROJECT
LINE-1 PHASE II PACKAGE A -15KM (JPY 17 B)
Duties : Responsible in the preparation of claims and variation order due to the changes in
the scope of work and actual field condition.
Check and evaluate the billings and accomplishment of Sub-contractors
Prepare monthly billings and monthly accomplishment report.
Update the schedule base on the monthly accomplishment.
Date : June 1, 2000 to May 31, 2005
Employer : MITSUBISHI HEAVY INDUSTRIES LTD. / SUMITOMO
CORPORATION/MECCS CORPORATION
Position : Quantity / Cost Engineer
Project : DESIGN AND CONSTRUCTION OF METRO MANILA STRATEGIC MASS
RAIL TRANSIT DEVELOPMENT PROJECT LINE -2 13.8 KM
PACKAGE 1 DEPOT (PHP 1.2 B)
Duties : Responsible in the preparation of the Bill of Quantities as per plans and Specifications of Site
Preparation, External Works, Workshop Building, MOW Building, Cafeteria Building, and at grade
track work.
Prepares change orders/actual quantity based on the revised plans and actual field condition, Monthly Progress Report and Interim Payment Certificate.
Check and evaluate the billings and accomplishment of Sub-contractors
Date : August 16, 1997 to May 31, 2000
Employer : DESIGN SCIENCE INC. /MITSUBISHI HEAVY INDUSTRIES LTD. /
SUMITOMO CORPORATION
Position : Quantity Engineer
Project : DESIGN AND CONSTRUCTION OF 16.95 KM EDSA –MASS RAIL TRANSIT
LINE III, NORTH AVENUE TO TAFT AVENUE VIA EDSA (465 M USD)
Duties : Responsible in the preparation of the Bill of Quantities as per plans and
Specification of all Station Buildings, Depot Building, at grade track work, Elevated track work
(via ducts) and Subway (tunneling).
Prepares change orders/actual quantity based on the revised plans and actual field condition.
Date : July 28, 1997 to August 15, 1997
Employer : DESIGN SCIENCE INC.
Position : Cost / Specification Engineer
Project : RESTORATION OF PHILIPPINES POST OFFICE BUILDING
LIWASANG BONIFACIO, MANILA
Duties : Responsible in the preparation of the Bidding Documents such as Instruction to
Bidders, Bid Requirements, Technical Specification and etc.
Prepares unit price analysis, quantity calculation and cost estimates in accordance with the
plans and specifications.
Date : January 1997 to July 1997
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer
Project : DETAILED ENGINEERING & DESIGN OF PREMIUMED II PROJECTS
CAUAYAN PUBLIC MARKET
ALICIA PUBLIC MARKET
DETAILED ENGINEERING & DESIGN OF IBRD – ASSISTED HIGHWAY MANAGEMENT
PROJECT UNDER DEPARTMENT OF PUBLIC WORKS & HIGHWAYS (DPWH)
RESTORATION OF MARAMAG-KIBAWE-KABACAN ROAD
(AGLAYAN DOLOGON SECTION & DAMULOG BY PASS)
Duties : Prepares quantity and cost estimates for the project in accordance with plans and
Specifications.
Prepares detailed analysis of all applicable unit prices using current cost, rental rates, bill of quantities, unit price analysis, etc.
Determine the major and minor causes of discrepancy in various cost estimates in order to arrive at realistic market prices.
Prepares the technical specification and special provisions, if any, to suit the requirements of the design.
Coordinates with other teams of experts that have similar interest in take-off and specification.
Prepares bidding documents and bid evaluation reports.
Undertake site visit and reconnaissance survey necessary in the preparation of plans and other bidding documents.
Date : January 1996 to December 1996
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer
Project : DETAILED ENGINEERING & DESIGN UPGRADING OF ROAD
NETWORK AND EROSION CONTROL AT THE FORMER CLARK AIR BASE
Widening of Mitchell-O’Leary Highway
Improvement of North Perimeter Road
Widening of Dyess Highway
Construction/Upgrading of Wagner-Dyess-Maryland Highway
Construction of Mitchell Bridge
Construction of Maryland Bridge
Erosion Control at Sacobia River
Erosion Control at Dolores River
Erosion Control at Sapang Bato River
Erosion Control between Mitchell-Dyess Junction
Duties : Prepare quantity and cost estimate in accordance with the plans and specification.
Prepare technical specification and other bidding documents.
Prepare unit price analysis per item of work.
Undertake site visit and reconnaissance survey necessary in the preparation of
Plans and other bidding documents.
Date : September 16, 1995 to December 31, 1995
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer
Project : CONSTRUCTION MANAGEMENT AND ENGINEERING SUPERVISION
ARMORING AND RAISING OF MANCATIAN RIGHT DIKE AT PORAC,PAMPANGA
Duties : Undertook pre-construction surveys prepare drawings, and made computations to
verify the construction quantities listed in the Bid Schedule.
Prepared cost estimate and other documents for the Change order to suit actual field condition.
Supervised and checked all the construction activities to ensure that it is in accordance with the plans and specification.
Prepare weekly accomplishment report of the project.
Reviewed and evaluated the construction schedule to assure the proper and smooth implementation of the project.
Date : May 16, 1995 to September 15, 1995
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer
Project : CONSTRUCTION MANAGEMENT AND ENGINEERING SUPERVISION
OF STO. TOMAS PROTECTIVE DIKE AT SAN MARCELINO, ZAMBALES
Duties : Undertook pre-construction surveys prepare drawings, and made computations to
verify the construction quantities listed in the Bid Schedule.
Prepared cost estimate and other documents for the Change order to suit actual field condition.
Supervised and checked all the construction activities to ensure that it is in accordance with the plans and specification.
Prepare weekly accomplishment report of the project.
Reviewed and evaluated the construction schedule to assure the proper and smooth implementation of the project.
Date : February 16, 1995 to May 15, 1995
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer
Project : DETAILED ENGINEERING & DESIGN OF ILAGAN PUBLIC MARKET (PREMIUMED II)
Duties : Prepared quantity and cost estimate in accordance with the plans and specification.
Prepare technical specification and other bidding documents.
Prepare unit price analysis per item of work.
Undertake site visit and reconnaissance survey necessary in the preparation of plans and other bidding documents.
Date : January 1995 to February 15, 1995
Employer : URABAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer
Project : DETAILED ENGINEERING & DESIGN FOR MPR-PMO 1995 FLAGSHIP PROJECTS
Duties : Prepared quantity and cost estimate in accordance with the plans and specification.
Prepare unit price analysis per item of works.
Assist in the preparation of technical specification and other bidding documents
Date : August 16, 1994 to December 1994
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer / Specifications Writer
Project : DETAILED ENGINEERINGF & DESIGN OF THE FOLLOWING PROJECTS:
Armoring and Raising of Mancatian Right Dike (IBRD Assisted Mount Pinatubo Rehabilitation Project)
NagbalayeBridge, Hilabangan Bridge and Abis Bridge, Negros Oriental (ADB-Assisted Fourth Road Improvement Project)
Duties : Prepared quantity estimate in accordance with the plans and specifications.
Prepared technical specifications and bidding documents.
Prepare unit price analysis per item of works.
Undertake site visit and reconnaissance survey necessary in the preparation of
plans, specification and other bidding documents.
Date : April 1994 to August 15, 1994
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Survey Engineer
Project : CONSTRUCTION MANAGEMENT AND ENGINEERING SUPERVISION
OF MT. PINATUBO REHABILITATION – PROJECT MANAGEMENT OFFICE (MPR-PMO)
INTERIM CONSULTANTS GROUP
Upgrading of Protective Dike at Macatian River
Desilting of Maubingan River
Duties : Undertook pre-construction surveys prepare drawings, and made computations to
verify the construction quantities listed in the Bid Schedule.
Prepared cost estimate and other documents for the Change order to suit actual field condition.
Date : January 1994 to March 1994
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Senior Cost Engineer
Project : MT. PINATUBO REHABILITATION – PROJECT MANAGEMENT OFFICE
(MPR-PMO) INTERIM CONSULTANTS GROUP
Duties : Prepared quantity estimates as per plans and specifications for roads, bridges,
Drainage system, water supply system, elevated water tank, sewerage system,
Buildings, earthworks and flood control system (dikes and slope protection).
Assisted in the preparation of technical specification and bid documents.
Prepare unit price analysis as per item of works.
Prepare weekly and monthly progress report.
Date : March 1992 to December 1993
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Survey Engineer
Project : CONSTRUCTION MANAGEMENT AND SUPERVISION OF MT. PINATUBO
EMERGENCY PROJECTS, 150-HECTARE SITE DEVELOPMENT INCLUDING
PRODUCTIVITYCENTERSAND VARIOUS BUILDINGS AT COMMUNITY CENTERS
BAMBAN RESETTLEMENT PROJECT (PHP 600M)
Duties : Prepared quantity estimates as per plans and specifications for roads, bridges,
Drainage system, water supply system, elevated water tank, sewerage system, buildings and earthworks.
Prepare unit price analysis as per item of works.
Prepare weekly and monthly progress report.
Prepare estimates and other necessary documents for change orders/supplemental orders.
Evaluated and checked monthly progress billing including all supporting documents prior to recommendation/ submission for payment.
Date : October 1991 to March 1992
Employer : URBAN INTEGRATED CONSULTANTS INC.
Position : Quantity / Cost Engineer
Project : DETAILED ENGINEERING DESIGN OF THE FOLLOWING:
MT.PINATUBOEMERGENCY PROJECTS
OLONGAPOCITY GENERAL HOSPITAL
BAMBAN RESETTLEMENT PROJECT
MAINANG RESETTLEMENT PROJECT
PORAC TALIPAPA PUBLIC MARKET
FLORIDABLANCA PUBLIC MARKET
40-BED EMERGENCY HOSPITAL – ANGELES CITY
HEALTH CENTERS
Duties : Prepared quantity estimates as per plans and specifications.
Estimated work variation orders of various projects
Evaluated bid proposals of qualified bidders in accordance with the evaluation
criteria and documentation procedures.
Prepare unit price analysis as per item of works of various projects.
Performed other related duties as directed by the supervisor.
Date : May 1990 to September 1991
Employer : PNG CONSTRUCTION AND DEVLOPMENT CORPORATION
Position : Project Engineer / Estimator
Project : PROJECT MANAGEMENT AND CONSTRUCTION SUPERVISION
WEDGEWOOD CONDOMINIUM AND TOWNHOUSES
INNSBROOK CONDOMINIUM
REEBOK SHOE FACTORY ( 9 INDUSTRIAL BUILDINGS)
NESTLE PHILIPPINES PLANT
VARIOUS PROJECTS
Duties : Prepared quantity and cost estimates as per plan and specification.
Assist in the preparation of billings for sub contractor.
Estimated work variation order for different projects.
Assist in canvassing of materials.
Undertake site inspection of prospective project.
Prepare Tender documents for bidding purposes.
Attended pre bid and bid conference as bidder's representative.
Directly supervised the implementation of civil and architectural works for
adherence to plans and specifications.
Prepare bill of materials and project budget.
Preparation and evaluation of monthly billings for approval of the monitoring
head.
Date : March 1987 to May 1990
Employer : PROVINCIAL ENGINEER’S OFFICE
Position : Civil Engineering Aide
Project : PROJECT MANAGEMENT AND CONSTRUCTION SUPERVISION
TABANG-BULACAN VIA BALUBAD ROAD
LIAS-LAMBAKIN ROAD
MEYCAUAYAN SERVICE ROAD
TUGATOG-LAWA ROAD
ABANGAN NORTE ROAD
MABINI ROAD
Duties : Work as an Engineer at Construction and Maintenance Division.
Inspect and supervise work under administration or by contract for adherence to
plans and specification of buildings, roads, bridges and maintenance.
Evaluate the monthly and weekly accomplishment reports of a certain project and
equipment.
Assist in the preparation of estimates, design, and bill of materials and program of
works and performed other related duties from time to time.
- Company:
- Industry:
- Job Role:
- Project:
- Region: