Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Lead Planning Engineer of Toshiba Corporation, Isogo Nuclear Energy System & Service Division, Yokohama Japan , Toshiba Corporation, OL4_ TeollisuudenVoimaOyj. Nuclear power Plant EPC Project of Finland

START Date: 
October, 2012
END Date: 
April, 2014

Organization

Position held

From

To

Project

Main responsibility

 

Quest Global

Pte. Ltd.

Posted at

Toshiba Corporation, Isogo Nuclear

Energy

System

& Service Division,Yokohama

Japan

through Singapore

based

Consultant

 

 

 

 

 

 

 

 

Lead Planning Engineer

 

 

Oct-12

 

 

Till Date

 

OL4_

TeollisuudenVoimaOyj.

 

Nuclear power Plant EPC Project of Finland

·  Making Schedule for Nuclear Power Plant Projects (EPC Projects) with the Help of Primavera (P6).

·  Preparing Composite Schedule.

·  Preparing Engineering Schedule.

·  Preparing Procurement and Delivery Schedule.

·  Preparing Construction Schedule.

·  Resource Loading and updating to the all type of schedule.

·  Making Project Schedule Management Plan.

·  Making Project Control Management Plan.