Planner/Scheduler, Mohammad Al-Barghash Trading & Contracting Company, Installation of Gas Pipeline and Scraper Facility

START Date: 
May, 2010

Reponsible in Preparing detailed baseline schedule based on the project requirements.

Plans, review and make thorough study of the project and define its requirements.

Collaborate with the Quantity surveyor to obtain the detailed quantities of the specific project.

Prepares execution plan on how to do the project required by the client and define whats the resources

are needed for each scope of work. And see to it that resources  are sufficient enough to complete the job.

And make sure that material availability will conform with project requirement.

Prepares Bi-Weekly, Monthly reports and calculate earned value costs and compare it with the baseline.

Discuss with Project Manger with any issues or risks that would affect the project and prepares back-up plan.

Checked if resource usage are just within reasonable schedule carefully avoiding imbalanced assignments.