Civil Engineer, Planning Engineer / Project Scheduler, Project Control Officer, Nam Theun 2 Power Co., Ltd., MRT Subway Project, Hydroelectric projects
Company Name: Nam Theun 2 Power Co., Ltd., Vientiane Lao PDR.
NTPC comprising of Electricité de France (EDF), Electricity Generating Pcl. (EGCO), Electricité du Laos (EDL) and Italian Thai Development Pcl. (ITD)
Period: July 2002-July 2010
Position held: Project Control Officer, Contract Officer, Project Schedule Engineer
Project: Nam Theun 2 Hydroelectric Power Project: Build-Own-Operate-Transfer Project. Project value 1.3 billion US dollars.
Reference: Mr. Tommy Bylund, Project Control Manager, Tel: (856) 21 263900
Duties and Responsibilities:
- Assist the Project Control Manager to update and reassess the budget of the Project.
- Follow up the expenditures comparing with the budget, forecast the incoming expenditures, and analyze the budget to minimize the cash flow problem.
- Prepare the monthly progress report
- Prepare contracts and validate the contracts payment.
- Develop Work Breakdown Structure (WBS) in conjunction with Project Management Team and Clients. The WBS forms the basis of the CPM Logic Diagrams.
- Responsible for coordination, preparation, monitoring and maintenance of the Nam Theun 2 Project Schedules in two parts; The Development Phase of the Project until Financial Close, and the Construction Phase into the Operation and Maintenance Phase.
- Responsible for Preparing detailed CPM Logic Diagrams in conjunction with Chief Executive Officer, Commercial and Contracts Manager and other Department Managers including monitors and updates the Schedule with actual hours expended and estimates to complete in conjunction with the Cost Controller.
- Highlights problem areas during schedule updates to the Commercial and Contracts Manager in order to minimize schedule impacts
- Provide scheduling system advisory services to other Branches of the organization.
- Assist the Commercial and Contracts Manager in the preparation and presentation of schedules that support the contractual position of the Project Company in any negotiations with its Contractors.
Company Name: SNMC Joint Venture, Bangkok Thailand
SNMC JV comprising of Kajima Corporation, Hazama Corporation, Maeda Corporation, Mitsui Corporation, Siam Syntech Pcl. TSB Trading Co. Ltd.
Period: June 1997 – June 2002
Position held: Civil/Office Engineer
Project: M.R.T. Chaloem Ratchamongkhon Line Project: The Design and Construction of the Depot.
Project value 6,300 million Baht.
Reference: Mr. Minorou Ishida, Project Manager, Tel: (66) 2 632 9300
Duties and Responsibilities:
- Planning, scheduling and monitoring the MRT Depot project including cost and resources using Primavera Project Planner software.
- Site supervision in the construction site.
- Produce monthly progress report and presentation of monthly progress meeting to the Project Owner to show the progress of work done.
- Coordinate with (sub) contractors and local authorities.
- Quantity survey.
- Supervise the computer network at the project office.
- Tendering schedule of G-MC-7A and G-MC-7B contract of Metropolitan Water Works Authority for water supply improvement.
Company Name: Thai Kajima Co. Ltd., Bangkok Thailand
Period: May 1995 – August 1995
Position held: Structural Engineer
Reference: Mr. Hiroshi Maesaka, Design Manager, Tel: (66) 2 632 9300
Duties and Responsibilities:
- Design and analyze the structural systems for steel and reinforced concrete structure such as factories and buildings.
- Recheck calculation sheet from designer consultants.
- Producing the structural calculation sheets of structural steel and concrete members using MS Excel spreadsheet.
- Quantity survey for the steel and concrete structure.