Site Planning Engineer, DSD Ferrometalco, 2x350 MW Thermal Power Project, 2x650 MW Thermal Power Project, Ammonia Nitrate Plant

START Date: 
October, 2009

Ø  July  2012 till now     ( Planning  Engineer )

Project:EHC-LDAN Ammonia Nitrate Plant

Company:  DSD FERROMETALCO                  Client: HASSAN ALLAM Construction (HAC)

Consultant:  UHDE                                            Owner: EGYPTION HYDROCARBON Corporation (EHC)

Duties:

·         Updating Schedule and making corrective actions according to the situation of actual work.

·         Preparing S-curves & Histograms for Weekly & monthly Progress Report.

·         Preparing (Daily, Weekly, Monthly) Man-hours Reports.

·         Following and monitoring all running activities at site

·         Review on site progress on day today basis and submitting reports to Client.

·         Coordinating with the logistics department for the shipping activities and priorities.

·         Making the reports of “Extra Work” done at Site.

 

 

Ø  July 2010 to June 2012     ( Planning  Engineer )

Project:ABU QIR Thermal Power Plant 2X650 MW Gas / Oil Fired Units.

Company:  DSD FERROMETALCO                           Client: ANSALDO CALDAIE

Consultant:  PGESCO                                                Owner: WDEPC

Duties:

·         Prepare Database for total Joints & Equivalent Inches for all Piping Systems in the Boilers

·         Follow-up all piping activities, monitoring & Updating progress for the running activities according to P&ID and Isometric DWG.

·         Follow- up Steel St. Progress according to DWG.

·         Review on site progress on day today basis and submitting reports to Client.

·         Preparing (Daily, Weekly, Monthly) Progress Reports.

·         S-curves & Histograms for Weekly & monthly Progress Report.

·         Breaking down the project activities into the minimum units (individual items).

·         Making the reports of “Extra Work” done at Site.

 

Ø  March 2010 to April 2010     ( Planning  Engineer )

Project:El-Tebbin Thermal Power Plant 2X350 MW Gas / Oil Fired Units.

Company:  DSD FERROMETALCO                           Client: ANSALDO CALDAIE

Consultant:  PGESCO                                                Owner: CEPC

Duties:

·         Follow-up all piping activities, monitoring & Updating progress for the running activities according to P&ID and Isometric DWG.

·         Preparing (Daily, Weekly) Progress Reports.

·         Preparing the daily (Man Hours / Man Power) Report.

·         Making the reports of “Extra Work” done at Site.

 

 

Ø  October 2009 to February 2010     ( Trainee  Engineer )

Project:El-Tebbin Thermal Power Plant 2X350 MW Gas / Oil Fired Units.

Company:  DSD FERROMETALCO                           Client: ANSALDO CALDAIE

Consultant:  PGESCO                                                Owner: CEPC