Deputy Planning Manager, Siemens Transportation Systems UK, Power Upgrade Project UK (Rail Electrification)

START Date: 
January, 2007
END Date: 
April, 2008

-          Production of fully cost loaded and resource levelled tender programmes.

-          Lead on feasibility study; Effectiveness of Time Chainage software (TILOS) within STS.

-          Forensic Planning; payment contention against delivery of various PUUK projects.

-          Senior planner for closing stages of Electrification PUUK (Power Upgrade UK) Project. Reporting weekly to NWR (P3).

-          Principal Planning NWR interface for Portsmouth SIMIS commissioning (MPP).

-          Training received on PMCS commercial system.