Site Engineer , TARIQ AL-GHANIM GEN. TRAD. & CONT. CO, Tank maintenance

START Date: 
September, 2005
END Date: 
July, 2012

     -prepare and plan the work program to meet client requirements

     - planning for the best productivity in a certain time and scope  

    -  Supervising the maintenance process of tanks  (Rebottoming,   Reroofing

            and shell replacement..

    - Aware of the deferent activity for tanks testing (tank Hydro testing,

       Pneumatic testing, Vacuum box  testing and NDT methods.

    -  Following the American petroleum institute’s procedures API (650)and (653

    - Dealing with the tanks painting systems and blasting process