Civil construction planning engineer, WBHO Construction, 16th Oxygen Train Substation

START Date: 
January, 2009
END Date: 
March, 2010

Contracts/Planning/Project Manager

16th Oxygen Train Substation

I was the manager in charge of the civil construction for the new 16th Oxygen Train Substation at the SASOL Secunda oil from coal plant. The contract was run under the NEC form of contract and the EPCM Contractor was Foster Wheeler.

I managed the project for WBHO Construction with a Contracts Manager and Senior Quantity Surveyor reporting to me. The construction works were planned using CCS Candy Siteplan. Progress was monitored and reported on weekly using the hours worked as the criteria. Each Early Warning (EW) and each Compensation Event (CE) was highlighted in the schedule separately and the effect calculated.

The project consisted of a Reinforced Concrete frame building with a Structural Steel roof structure over. Brick infill was used to close the building.