Mechanical Engineer, Science-Tech Solutions Sdn Bhd, As per above
START Date:
May, 2006
END Date:
December, 2007
| Project Title | Duration | Position |
1 | PSR-2 Revamp Project – Miscellaneous Enabling Works | Nov 2007 – Dec 2007 | Quantity Surveyor |
2 | 13th Petronas Methanol (Labuan) Sdn Bhd Turnaround 2007 | Oct 2007 – Nov 2007 | Cost Engineer / Assistant Scheduler |
3 | HSE Management System towards the certification of ISO14001 and OHSAS 18001. Qualified Internal Auditor for ISO14001 and OHSAS 18001 | Jan 2007 – Oct 2007 | HSE Committee Team Leader |
4 | Interactive CD complete with Manual for Induction Course for Foreign Workers for Department of Skill Development, Ministry of Human Resources | May 2006 – Dec 2006 | Project Coordinator |
- Company:
- Industry:
- Job Role:
- Project:
- Region: