President, Project Manager, Planner, Cost Controller , PMO Soluciones, Various projects
START Date:
December, 2005 - Managed a portfolio of 11 projects (USD 3.5 M) completing 95% of the projects on time, within budget and client acceptance.
- Oversaw elaboration and maintenance of project schedules with appropriate resource loaded activities and cost control plans; prepared WBS, OBS, RBS and level 4 schedules using MS Project and Primavera; identified and highlighted potential bottlenecks and suggested remedial measures; developed and implemented the risk matrix and response, drafted the cash flow reports and provided early warning support to management.
- Implemented a PMO office, developed PMO documents and methodology and managed all stages of the projects for a software development company saving 20% on budgeted costs.
- Provided PMO manpower for companies like SAF, SMS Consultores, CINET Consulting and Previsora Insurance.