Project Controls Engineer, Iberdrola Engineering&Construction, Several Projects
START Date:
August, 2003
END Date:
May, 2005 Project Controls Engineer. Main projects and functions:
CCGT Castellón 4 (850 MW, €350 M): Project Controls Engineer.
BCC Tunisia (T&D, €30 M): Project Controls Engineer based in Tunis.
CCGT Santurtzi (400 MW, €200 M): Owner Cost Control Engineer.
Schedule preparation or Thermal Generation Power Plants proposals.