Application Engineer, Swagelok USA - Baroda Fluid System Component, Various
START Date:
June, 2004
END Date:
December, 2006 AAssist Planning Manager in schedule development in line with engineering and construction team feedback
ACompilation and regular updating of contractual control schedule as well as deliverable compilation
A Support the lead planning engineer in Critical Path Analysis routines
APreparation of progress monitoring reports such as S Curves, Summary tables, Site Progress, Daily Progress and Weekly Progress Reports
AAssist Project Manager by participating in the weekly and monthly contractor review meetings with clients, subcontractors and vendors
AActive participation in Project related Health and Safety Aspects
Experience Hours (Planning & Scheduling):
3800
Experience Hours (Cost Management):
1300 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: