Senior Planner, Foster Wheeler France, EXXON POLYETHYLENE AND POLYPROPYLENE PROJECT
START Date:
August, 1990
END Date:
February, 1992
- 1990 - 1992 FOSTER WHEELER, FRANCE
SENIOR PLANNING ENGINEER
POLYETHYLENE & POLYPROPYLENE PLANT
Developed a Level 3 Schedule and integrated reporting system on Artemis 7000, with automatic generation of Level 2 and Level 1 schedules and progress curves, and reporting to the client, Exxon. Subsequently for one of the six processing units, became actively involved in coordinating Contractor schedules, developing and monitoring progress measurement systems, material take-offs and man-hour estimates. Also monitored material and equipment deliveries.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: