Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Senior Planner / Senior Planning Engineer, Sasol Technology, FTWEP - Sasolburg

START Date: 
June, 2013

Responsibilties             

 

 

  • Prepare Upfront Programmes
  • Set up project calendar
  • Set up Activities and Coding with construction managers
  • Set up resource requirements using ALEC standard outputs
  • Sequence & link the required activities, within given milestones.
  • Establish the critical path through the programme
  • Prepare information schedule in conjunction with construction manager
  • Prepare subcontract appointment schedule with construction manager
  • Progress monitoring and updates
  • Regular progress recording on site of actual progress
  • Record & report actual progress against target programme
  • Preparation of required reports for construction managers
  • Interpret data and identify bottlenecks with construction manager
  • Predict completion dates and prepare "Look-ahead" reports
  • Monitor resources and Key Performance Index items (KPI's)
  • Create baseline resource curves
  • Record actual against planned on resource curves & KPI's
  • Create records of actual progress of KPI's
  • Sub Contractor programmes
  • Examine and report on subcontract programmes
  • Ensure subcontract programmes are in line with site requirements
  • Monitor subcontract work against programmes
  • Report on subcontract progress to construction managers
  • Working Programmes
  • Establish working programme requirements with construction managers
  • Prepare working programmes in consultation with site supervision
  • Monitor & report on working programmes
  • Revise working programmes where required by construction managers