Senior Planner, World Construction Services for EDISON S.p.a., “ Vega Oil Project” - Edison S.P.A. EPC Senior Planner responsible for Large modification relevant Tanks storage boat linked with platform on Mediterranean Sea.
START Date:
January, 2008
END Date:
January, 2009 “ Vega Oil Project” - Edison S.P.A. EPC Senior Planner responsible for Large modification relevant Tanks storage boat linked with platform on Mediterranean Sea.
It was developped on Siracuse Head-quarterand Trieste (Italy) FINCANTIERI and at the end the connection with plattform on Mediterranean Sea.
P5 Detail Schedule preparation and managing, EPC foll-up, Preparation and monitoring of all activities for client reports.