Lead/Senior Planning Engineer, Balfour Beatty, Bulls Lodge 400kV substation
Senior Planning Engineer, Balfour Beatty, Power Transmission & Distribution
· Site-based role with greater hands-on experience.
· Project: Construction of a new 400kV substation & cable connection to a new 25kV ATFS (Auto
Transformer Feeder Station) – Client: National Grid (Ultimate Client: Network Rail).
· Successfully undertaken day to day detail project planning and progress monitoring of all work
packages - from contract award to commissioning and demobilisation - including:
o Civil: civil foundations of all the equipment, Substation control room building, amenity
building, approx. 2 km of road between the two substations.
o OHL:buildingtwonewtowersandturn-intothesubstation.
o Cable:installationofapprox.2kmofcablefrom400kVto25kVsubstation.
o StructurefortheprimaryequipmentincludingCSE(cablesealingend).
o M&E: mechanical and electrical installation of the primary equipment including
disconnector, circuit breaker, earth switches, current transformer, voltage transformer.o Stage1and2commissioning
· Successfully maintained the quality of the programme according to the required standard for NEC - Option C - contracts to enable successful claims.
· Provided detail analysis for programme impact of early warnings (EWA), compensation events (CE) and other unfavourable events (such as inclement weather) during the lifecycle of the projects.
· Proactively communicated the programme with wide variety of stakeholder including: Suppliers (such as electrical suppliers: ABB, GE, Prysmian, Wardpower, PE System, Siemens) Civil subcontractors (Neary , Matrix Renewables) , Clients and Internal stakeholders (QS, PM, Contract manager, designers, Site manager, engineers).
· Updated progress of the activities and submitted the programme update to the client (National Grid) monthly according to client's specification (TP193) and expectations.
· Improved client’s scoring on programme by over 50% since joined the project.
· Participated in risk & opportunity review meetings by highlighting programme risks and evaluating
time impact of risks introduced to the project.
· Earned value analysis (EVA); produce SPI reports and advise stakeholders of early indication of
programme delays, potential impact and agree mitigation plans with them.
· Maintaining baseline register to manage baseline changes according to approved CEs and re- baselining as required aligning programme with site progress and sequence of work on site upon client’s approval.
· Continuous programme review to assure schedule quality and avoid scope creep.
· Assisted QS with forecasting by providing breakdown of monthly planned value and earned value
based on progress updates.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: