Project Controls Engineer, CH2M Hill VECO Engineering Abu Dhabi UAE, FEED for El M'Zaid Project Surface Facilities

START Date: 
August, 2013

Working as Project Controls Lead for the following projects:                  

                                   

1)     FEED for El M’Zaid Project Surface Facilities (Client: Groupement El M’Zaid (Sonatrach-CNPC), Algeria)

2)     ASAB Facilities Upgrade Study (Client: Abu Dhabi Company for Onshore Oil Operations – ADCO, Abu Dhabi)

3)     On-Call Technical Services Agreement (Client: Dolphin Energy Limited, Qatar)

 

The main responsibilities are the project controls functions such as:

 

·            Owns and complies with the CH2MHILL’s policies

·            Establishing the project baseline budget (revenue and cost) by preparing Cost Break-down Structure (CBS) in the Pricer

·            Preparation of Engineering (Feasibility Study, FEED, EPC) schedules base on SOW

·            Early forecast of potential problems affecting the key project milestones and completion date

·            Provide support to project managers in preparation of EOT claims, variation orders, contractual correspondence etc

·            Participate in preparation of resource utilization on different projects & preparation of corporate reports for resource requirements for on-going and future project

·            Wrench set-up, monitoring and control for project design deliverables

·            Critical path analysis (CPA) on the basis of agreed schedule

·            Establishing and effective implementation of the systems for the tracking of cost and progress

·            Prepared analysis/ efficiency reports (GM analysis of revenue verses cost incurred, progress and variation orders) for Management review

·            Established and maintained the cost trending system to analyze the impact of variation orders on baseline revenue, cost and schedule

·            Progress variance analysis (baseline, current and mitigation schedule)

·            Engaged in the mitigation strategy to minimize the potential risk/bottlenecks and delays

·            Prepared EPC schedules at engineering stage

·            Engaged in risk identification, analysis and mitigation strategy on of Feasibility Study, FEED and EPC jobs