Planner or Senior Planner, Dragados Offshore SA, CASTOR PROJECT

START Date: 
January, 2010
END Date: 
December, 2010

planning engineer, dragados offshore, castor  ugs (kiewitt) project- 2010
Project Detail:  Jacket & Piles Fabrication.

Planner Engineer for Ternder Department.

Scheduling, Baselines, Current Schedules, Progress Control