Planning & Project Controls Engineer, Decmil Australia, LNG Plant - WHEATSTONE Australia: owner Chevron

START Date: 
November, 2010

Project Controls Engineer

 

  • Concurrently manage multiple work packages.
  • Development of Work Breakdown Structure, Tender, Baseline and Construction programmes, Progress S-Curves and Rule of Credit.
  • Carry out project Scope Management, Earned Value Analysis, Resource Balancing and Subcontractor Management.
  • Lodgment of Delay Notices, Extension of Time and Contract Variation Requests.
  • Establish and maintain relationships with Client’s Project Controls personnel. 
  • Monitoring, updating and reporting on construction progress and productivity.
  • Guiding and managing graduate / junior engineers and planning consultants.