Project Planning Manager / Lead Planner, Murray & Roberts Projects, Kusile Power Station

START Date: 
August, 2010
END Date: 
August, 2015

Development implimentation and maintenance of project planning, measurement, reporting and control systems for a new 6 x 800MW unit coal fired power station.

Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
1000