Project planner and Cost control, Caspian Investment and Development corporation, Construction of Baku Paper Plant

START Date: 
August, 2010
END Date: 
June, 2011
  • Responsible for the Project planning, time planning and milestone targets, as well forecast of financial resources plan, contract payment schedule
  • Take part in the design meeting and preparations as well all negotiations of contract and project works to be able to make the overall planning, expedite and coordinate the works, in strong cooperation with the Construction Manager, Electrical, Mechanic and Process Engineer
  • Taking part of the periodical (weekly) project meetings, responsible for minutes of the meeting and follow up expedite actions
  • Coordinating and communicating concerning the progress of the works with internal project group members, contractors, machine suppliers during machine production, transport and installation
  • If needed initiate corrective actions , or informs the project management to expedite works
  • Keep records of all contracts, total project budget and follow up of spending: provide to financial department the forecast of future payments
  • Will be the main intermediary for all designers, consultancy technical experts, contractors, machine suppliers, process equipment installers for timing and planning issues
  • Follow the supply, import, custom clearance of equipment for the project in cooperation with the procurement department
  • The scope of works will in a second stage also include the planning and follow up of the whole plant staff, recruitment and training process, materials sourcing. Commissioning, start up and implementing the final working plant organization with procedures and systems