SENIOR PLANNER, Engineers India Limited, GNL-2K, PIPELINES, CRACKER & POLYMER PROJECTS, REFINERY EXPENSION,SHUTDOWN PLANNING & EXECUTION,NAPHTHA CRACKER PROJECTS

START Date: 
July, 2003
 
PROFESSIONAL EXPERIENCE

 

Total Experience:      7.7 Years, out of which 2.0 years in Engineers India Limited.
 
 
CAREER SUMMARY

 

Over 7 years of experience in Project Planning & Monitoring  at Home Office and Construction sites in India for Heater Package, Delayed Coker Unit and Cross country Pipelines.

 

Presently working as Sr. Planning Engineer at Site office scheduling for Brahmaputra Cracker & Polymer Project, Panipat Naphtha Cracker Project, Panipat Refinery Expansion Project. Cross country Pipelines Project.

 

My responsibilities include the Planning and Project Control work for all phases of Project viz. Engineering, Procurement and Construction for achieving desired goal set jointly with Client/Owner. Major activities include development of weighed values and Work Breakdown Structures for different phases of Project, preparing overall project schedule and monitoring the same, follow up of potential slippages areas and taking remedial measures. Also responsible for liaisoning with Client/Owner and different Contractors / Vendors,  approval of work schedules to control the Project cost & generate various reports indicating project schedule vis-a-a progress of work, identification of areas of concern and their remedial measures, monitoring & co-ordination of engineering / procurement activities of contractors.

 

Wide & proven experience on providing Project monitoring services under EPCM (Engineering, Procurement, Construction and Management) and Project Management Consultancy (PMC) scope of services with the extensive use of various Computer software’s like PRIMAVERA (EC Version) and In-House Packages.

 

 

 
FIELDS OF EXPERIENCE

Executed Projects of Cross Country Pipelines, Heater Packages and Delayed Coker Unit.

Co-ordination of Planning , Scheduling, Monitoring and Progress reporting functions for Refinery, Petrochemical, Pipeline projects, covering development, finalization and implementation of following Planning deliverables.

  • Proposal Schedules
  • Project Execution Philosophy
  • Project Work Breakdown Structure
  • Overall Project Schedule
  • Project Networks of various levels
  • Functional / Discipline-wise Schedules
  • Progress Measurement System
  • Construction Planning
  • Contractors Schedules
  • Shutdown Schedules
  • Material Planning & Control
  • Monthly Progress Reports
  • Monitoring & and follow up of project activities
  • Monitoring reports & Reviews
  • Recovery plans & Catch up Schedules
  • Reviewing performance of LSTK contractors
  • Review meetings & Presentations

WORK HISTORY

Job involves responsibilities for Multi Projects Planning, Scheduling and Monitoring of Pipeline Projects details given hereunder.

 

  1. ENGINEERS INDIA LIMITED:  

             JANUARY 2009   TO TILL DATE (2.0 YEARS)

 

- GNL-2K PROJECT

   CLIENT :  SONATRACH LTD.

Job Title

:

Sr. Planning Engineer (Const. Site)

Period 

:

JUNE. 2010-TILL DATE

Project phase

:

Planning & Monitoring of Project.

 

  • To study the input documents for development of contractor’s schedules and man hour estimates for inclusion in proposals in consultation with the proposal coordinator and other documents.
  • Development of WBS, Networks, Bar charts schedules, Document control index, progress statistics and progress curve (s-curves).
  • In primavera overall project schedule, project WBS, progress, measurement methodology, detailed overall project schedule, functional schedule .(discipline wise DCI /MCI, Procurement), progress “s” curves, manpower and machinery deployment schedule.
  • Preparation & Analysis  Procurement, Manufacturing/Fabrication/ Construction, Installation, Hook-up, Testing & Commissioning Schedules on Primavera Project Planner
  • Preparation and Formulation of Work Breakdown Structure.
  • Preparation of Progress Measurement System
  • Developing Histograms and Overall Physical Progress “S” curves.
  • Develops, maintains and updates Integrated Project Master Schedule as well as schedule analysis.

 

-  BRAHPUTRA CRACKER & POLYMER PROJECT

   CLIENT :  BRAHPUTRA CRACKER & POLYMER LTD

 

 

Job Title

:

Sr. Planning Engineer (Const. Site)

Period 

:

JUNE. 2009 – JUNE.2010

Project phase

:

Planning & Monitoring of  Project.

 

Responsibilities  involve the development of  Overall Project & Construction Schedule,  S-curve, Weighted values of activities for reporting percentage progress, Co-coordinating activities of all disciplines on their day to day operations, liaison with disciplines, initiate progress meetings with client and contractors, generate different reports, coordinating and monitoring all phase of construction in line with the targets/schedules, identifying troubled spots and developing action plan in consultation with client to eliminate those for expeditious completion of work, preparing different status reports and presentation materials for EIL’s & Owners management information.

  • To study the input documents for development of contractor’s schedules and man hour estimates for inclusion in proposals in consultation with the proposal coordinator and other documents.
  • Development of WBS, Networks, Bar charts schedules, Document control index, progress statistics and progress curve (s-curves).
  • Project planning in preparing, updating and implementing department manual & work procedures.
  • In primavera overall project schedule, project WBS, progress, measurement methodology, detailed overall project schedule, functional schedule .(discipline wise DCI /MCI, Procurement), progress “s” curves, manpower and machinery deployment schedule.
  • Preparation of Project Planning & Scheduling.
  • Preparation of Engineering, Procurement, Manufacturing/Fabrication/ Construction, Installation, Hook-up, Testing & Commissioning Schedules on Primavera Project Planner
  • Preparation and Formulation of Work Breakdown Structure.
  • Preparation of Progress Measurement System
  • Preparation of Weight point allocation.
  • Preparation of Weekly Progress Report.
  • Preparation of Monthly Progress Report.
  • Preparation of Daily Progress Report.
  • Developing Histograms and Overall Physical Progress “S” curves.
  • Develops, maintains and updates Integrated Project Master Schedule as well as schedule analysis.
  • Preparation of Monthly Progress Presentations for review meetings with client.

 

-  PANIPAT NAPHTHA CRACKER PROJECT

   CLIENT :  INDIAN OIL CORPORATION LIMITED

 

Job Title

:

Sr. Planning Engineer (Project Serv.)

Period 

JAN.2009 – JUNE.2009

Project phase

:

Planning & Monitoring of Project.

 

Responsibilities involve the development of Overall Project & Construction Schedule, S-curve, Weighted values of activities for reporting percentage progress, Co-coordinating activities of all disciplines on their day to day operations.

  • Preparation of Project Planning & Scheduling.
  • Preparation of Engineering, Procurement, Manufacturing/Fabrication/ Construction, Installation, Hook-up, Testing & Commissioning Schedules on Primavera Project Planner
  • Preparation and Formulation of Work Breakdown Structure.
  • Preparation of Progress Measurement System
  • Preparation of Monthly Progress Report.
  • Developing Histograms and Overall Physical Progress “S” curves.
  • Develops, maintains and updates Integrated Project Master Schedule as well as schedule analysis and risk analysis.

 

 

-  PANIPAT REFINERY EXPENSION PROJECT

   CLIENT :  INDIAN OIL CORPORATION LIMITED

 

Job Title                   

:

Sr. Planning Engineer (Project Serv.)

Period 

:

JAN.2009 – JUNE.2009

Project phase         

:

Planning & Monitoring of Project.

 

Responsibilities involve the development of Monthly progress report, Action taken reports, Delay analysis, and Project performance reports. Responsibilities involve the development of Overall Project & Construction Schedule, S-curve, Weighted values of activities for reporting percentage progress, Co-coordinating activities of all disciplines on their day to day operations.

  • Preparation of Project Planning & Scheduling.
  • Preparation of Engineering, Procurement, Manufacturing/Fabrication/ Construction, Installation, Hook-up, Testing & Commissioning Schedules on Primavera Project Planner
  • Preparation and Formulation of Work Breakdown Structure.
  • Preparation of Progress Measurement System
  • Preparation of Monthly Progress Report.
  • Developing Histograms and Overall Physical Progress “S” curves.
  • Develops, maintains and updates Integrated Project Master Schedule as well as schedule analysis and risk analysis.

 

 

                         

 

  1. PREVIOUS WORK HISTORY ( 5.7 YEARS)

             PUNJ LLOYD LTD.  : 

             FEBRUARY-2008 TO DECEMBER-2008 (11 MONTHS)

 

-  KENYA PIPELINE EXTENSION PROJECT.

   660Km (16”) of  1.721 MMTPA – MULTI  PRODUCT  PIPELINE

   CLIENT :  KENYA PETROCHEMICAL LTD.

 

Job Title

:

 Sr. Planning Engineer (P/L Division)

Period 

:

OCT.2008 –DEC.2008

Project phase

:

 Planning & Monitoring of Project. 

 

Responsibilities  involve the development of  Overall Project & Construction Schedule,  S-curve, Weighted values of activities for reporting percentage progress, Co-coordinating activities of all disciplines on their day to day operations, liaison with disciplines, initiate progress meetings with client

  • Preparation of Project Planning & Scheduling.
  • Preparation of Engineering, Procurement, Manufacturing/Fabrication/ Construction, Installation, Hook-up, Testing & Commissioning Schedules on Primavera Project Planner
  • Preparation and Formulation of Work Breakdown Structure.
  • Preparation of Progress Measurement System
  • Preparation of Weight point allocation.
  • Preparation of Weekly Progress Report.
  • Preparation of Monthly Progress Report.
  • Preparation of Daily Progress Report.
  • Developing Histograms and Overall Physical Progress “S” curves.
  • Develops, maintains and updates Integrated Project Master Schedule as well as schedule analysis and risk analysis.
  • Preparation of Monthly, Weekly Progress Presentations for review meetings with client.

 

 

-  PANVEL PIPELINE PROJECT PHASE-II, DABHOL.  

   980 Km (18”) & 73 Km (16”)  of  5MMTPA – MULTI PRODUCT  PIPELINE 

       CLIENT :  HINDUSTAN PETROLEUM CORPORATION LIMITED

 

Job Title

:

 Sr. Planning Engineer (P/L Division)

Period 

:

FEB.2008-OCT.2008

Project phase

:

 Planning & Monitoring of Project. 

 

Responsibilities  involve the development of  Overall Project & Construction Schedule,  S-curve, Weighted values of activities for reporting percentage progress, Co-coordinating activities of all disciplines on their day to day operations

  • Preparation of Engineering, Procurement, Manufacturing/Fabrication/ Construction, Installation, Hook-up, Testing & Commissioning Schedules on Primavera Project Planner
  • Preparation and Formulation of Work Breakdown Structure.
  • Preparation of Progress Measurement System
  • Preparation of Weekly Progress Report.
  • Preparation of Monthly Progress Report.
  • Preparation of Daily Progress Report.
  • Developing Histograms and Overall Physical Progress “S” curves.
  • Preparation of Weekly, Monthly Progress Presentations for review meetings with client.

 

                 

 

  1. INDIAN OIL CORPORATION LIMITED.

             OCTOBER -2004 TO JANUARY- 2008   ( 3. 4 YEARS)

 

-  SHUTDOWN OF FCCU,CDU,VDU,SRU,RFCCU UNITS

Job Title

:

 Sr. Planning Engineer (Refinery Division)

Period 

:

OCT.2004 –FEB.2008

Project phase

:

Planning & Monitoring of Project During Shutdown period in different units Of Indian Oil Corporation Ltd. like as Panipat , Mathura , Barauni, as a Mechanical Maintenance Engineer.(Planning) on static equipment like as heat exchanger, column, vessels, reactor, furnace, regenerator, valves etc.

Development of  Overall Project & Construction schedule, Contractor schedule, S-Curve, Weighted values of activities for reporting percentage progress, Coordinating activities of all disciplines on their day to day operations, liaison with different disciples, initiate progress meetings with client and contractors, generate different reports, coordinating and monitoring all phases of construction in line with the targets/schedules, identifying troubled spots and developing action plan.

  • Using primavera to reduced the time during the shutdown activities.
  • To make bar chart of activities & WBS (work breakdown structure) for all plant activities.
  • Using SAP for material issue voucher (MIV) & Contract labor index line up.
  • Supervision & monitoring of job during maintenance & cross-check with inspection.
  • Executing the activities like ring test, tube test, below, economizer coil super heater coil installation, hydro testing, demister paid repairing, tray installing, cleaning, buffing, nozzles welding

(Rot run, DP,SR) etc.  

  • Make daily progress report & day by day activity chart to perform the operation.
  • To attend the review meetings with client engineers & give the demonstration of scheduling.
  • Site seen at the time of execution in piping and structural & equipment, erection & fabrication, revamping & modernization the process piping.