Senior Planning and Scheduling Engineer, Sayed Hamid Behbehani & Sons Co. W.L.L. JV w/ SK Engineering and Construction, Oil and Gas, Lexus show room, Al Khalid tower...etc.
START Date:
September, 2000
END Date:
October, 2008
SK Engineering, Construction & Sayed Hamid Behbehani and Sons Company
Senior Planning Engineer (Kuwait Feb 2006 – Oct 2008).
Duties and Responsibilities:
- Planning and scheduling
- Master Construction Schedule (Executive management summary level).
- Define the Project Scopes
- Establish the work, resource and organization breakdown structures (WBS, RBS, and OBS).
- Establish timeline, logical relationship and sequences of deliverables.
- Determine the budget of each component activity, work package and group of tasks.
- Provide project execution approaches/methodologies (Quantity analysis and Constructability analysis).
- Identify the project milestones and key events.
- Provide detailed project baseline schedule, cash flow, S-curve, resource histograms, basic of schedule is documented.
- Provide materials, drawings, subcontractors and suppliers control plans
- Establish measuring and evaluation processes for schedule.
- Schedule Management and Control
- Implement schedule management and control procedures.
- Maintaining the schedule during the project execution phases by:
- Tracking progress by updating the project schedule on regular
basis to assess actual performance against the plan. - Assess impact on the critical path and near-critical activities and
report critical work activities to project management. - Monitor schedule deviations and variances and assist in
developing alternative methods for corrective actions. - Perform value analysis upon recommended alternatives to determine
cost/benefits tradeoff, and request recommendations to project management. - Revise the schedule as directed by the project management and ensure that the schedule changes are communicated to all project team members.
- Schedule coordination and communication by:
- Present and answer questions on project plans and schedule at project meetings.
- Perform analysis to evaluate alternative plans, work-around courses of action, otherwise, amend, plan, schedule.
- Work in concept with the project cost engineers, quantity surveyors, estimators, and materials control personnel, to ensure cost and schedule integration.
- Schedule change management by:
- Revise the approved baseline schedule only when a change order indicates a change in scope or duration.
- Keep time-phased copies of the schedule of the work as historical records as the project progress.
- Provide schedule-related recommendations to the project management team on strategies to recover from the project delays.
- Schedule reports and deliverables by :
- Perform schedule analysis and provide periodic (daily, weekly, fortnightly, monthly, Quarterly, semi-annual, annual) current/ahead status reports of schedule content to the project management team.
- Issue status updates and approved revisions of the schedule that reflect work progress and time elapsed.
- Project and schedule closeout by:
- Upon completion of the project, verify that the as-built schedule reflects accurate completion dates for each schedule activity.
1.Lexus showrooms and facilities.
- Owner:El Sayer Group (Local Authorized Agency in Kuwait for Toyota and Lexus Cars)
- Total Budget:8,624,319.650KD (31,430,000 $)
- Project Duration: 2 years (24 months, 730 days).
2.Intercontinental Hotel.
- Owner:Central International for Hotels Company(CIHC).
- Total Budget:33,200,000 KD (120,000,000 $).
- Project Duration: 4 years (48 months, 1460 days).
3.Facility Upgrade and Relocation of Under Ground Process Piping for Gathering Centers (GCs) 1,2,9,10,11,16,17,19,20,22 & BS 170(Group B) - (KOC Contract No. 26422).
Owner:Kuwait Oil Company (K.O.C).
- Total Budget:357,091,140.000 K.D (1.3 Billion $).
- Project Duration: 5 years (60 months, 1825 days).
4.Aerated Concrete Production Plant in Shouaba.
- Owner:Union Construction Material Manufacturing Company
- Total Budget:5,580,000 KD (20,000,000 $).
- Project Duration: 1.5 years (18 months, 730 days).
5.Al Khalid Residential Tower.
- Owner:Al-Khalid Real Estate Company.
- Total Budget:7,550,268.500 KD ( 27,516,000 $)
- Project Duration: 2 years (24 months, 730 days).
6.Northern Sabriya Substation.
- Owner:Kuwait Oil Company (K.O.C).
- Total Budget:2,900,000 KD (10,000,000 $).
- Project Duration: 1.5 years (18 months, 480 days).
7.
GC-24 Project -Building of new gathering center GC-24 at sabriya fields north Kuwait.
- Owner: Kuwait Oil Company (K.O.C).
- Total Budget:185,000,000 K.D (673 Million $).
- Project Duration: 2.5 years (30 months, 900 days).
Al Daleel General Trading & Contracting Company
Project Engineer and Project Planner (Kuwait Jan 2005- Feb 2006).
Duties and Responsibilities:
- Acting as the main technical adviser on a construction site for subcontractors, crafts people and operatives.
- Setting out, leveling and surveying the site.
- Checking plans, drawings and quantities for accuracy of calculations.
- Ensuring all materials used and work performed are as per specifications.
- Overseeing the selection and requisition of materials and plant.
- Managing, monitoring and interpreting the contract design documents supplied by the client/architect.
- Liaising with any consultants, sub-contractors, supervisors, planners, quantity surveyors and the general workforce involved in the project.
- Day-to-day management of the site, including supervising and monitoring the site labor force and the work of any subcontractors.
- Planning the work and efficiently organizing the plant and site facilities in order to meet agreed deadlines.
- Overseeing quality control, health and safety matters on site.
- Preparing reports as required on daily, weekly, fortnightly, monthly basis.
- Resolving any unexpected technical difficulties, and other problems that may arise.
- Technical Evaluations & Reviewing for Projects Performance.
National Bank of Kuwait (NBK-Rawda Branch and Salmiyah Branch).
- Owner:National Bank of Kuwait (NBK)
- Total Budget:575,145 K.D (2,103,498 $).
- Project Duration: 7.5 months, 225 days).
RK International Company
Planning Engineer (Kuwait March 2003 - Dec 2004).
1.Super Market and Offices Co-operative Society of Police.
- Owner:Ministry of Interior Police Society of Consumerism
- Total Budget:1,970,000 K.D (7,201,000 $).
- Project Duration: 20 months (600 days).
2.
Qadssia Swimming Pool Complex.
- Owner: Kuwait Public Authority for Youth and Sport.
- Total Budget:2,936,000 K.D (10,777,000 $)
- Project Duration: 22 months (670 days).
Al-Ghanim International Company
Site Engineer (Kuwait Jul 2001 - Dec 2002).
Duties and Responsibilities:
- Following up and coordinating with other related Bid packs for the civil works & Construction progress in accordance with; Contract documents and Specifications, Centralized system of planning, organizing, controlling, Safety precautions and Quality assurance and control systems.
- Acting as the main technical adviser on a construction site for subcontractors, crafts people and operatives.
- Setting out, leveling and surveying the site.
- Checking plans, drawings and quantities for accuracy of calculations.
- Ensuring all materials used and work performed are as per specifications.
- Overseeing the selection and requisition of materials and plant.
- Managing, monitoring and interpreting the contract design documents supplied by the client/architect.
- Liaising with any consultants, sub-contractors, supervisors, planners, quantity surveyors and the general workforce involved in the project.
Day-to-day management of the site, including supervising and monitoring the site labor force and the work of any subcontractors.
- Planning the work and efficiently organizing the plant and site facilities in order to meet agreed deadlines.
- Overseeing quality control, health and safety matters on site.
- Preparing reports as required on daily, weekly, fortnightly, monthly basis.
- Resolving any unexpected technical difficulties, and other problems that may arise.
Kuwait Oil Sector Complex Bid Packs 3, 7 and 8.
- Owner:Kuwait Petroleum Company Corporation, Corporate Projects Department.
- Total Budget:60,500,000 K.D (220,440,825 $).
- Project Duration: 36 months (1095 days).
AL Qahtany Company
Site Engineer (Kuwait Sep 2000 - June 2001).
Construction, Building and Maintain of 307 Welfare Public Houses at Al Addan area, with its main infrastructures and services.
- Owner: Public Authority for Housing care.
- Total Budget:13,000,000 K.D (43,000,000 $)
- Project Duration: 22 months (670 days).
Computer Skills:
- Excel
- Word
- PowerPoint
- Microsoft Project 2010
- AutoCAD 2008
- Primavera V.2, 3, 3.1
- Claim digger V.3.3
- Primavera V.6e, V6.7
- Contract Manager V.12
- 3D Landscape
- Scala info channel Designer.
- Operating Systems: Windows7, vista, XP.
Spoken Language:
- Arabic
- English
Professional Training Courses:
- Project Management for Engineering and construction.
- SMC-Strategic Management in construction.
- PMP-Project Management Professional.
- PSP-Project Scheduling Professional.
- Safety HSE.
- Quality Assurance Quality Control.
- Technical Report Writing and Evaluations.
Professional affiliations and memberships:
- Egyptian Engineering Syndicate, EES
- Kuwait Society of Engineers, KSE
- Project Management Institute, PMI
- Construction Management Association of America, CMAA
- Association for the Advancement of Cost Engineering, AACE International
- Society devoted to the Advancement of the Value Engineering, SAVE International
- American Society of Civil Engineers, ASCE
- Construction Financial Management Association, CFMA
- International Association of Project & Program Management , IAPPM.