CONSTRUCTION/PLANNING ENGINEER, Reliance Industries Ltd, Jamnagar Export Refinery project
START Date:
May, 2006
END Date:
January, 2011 1. Monitoring of daily activities to be executed.
2. Updating in Datatabase
3. Publishing Status report in form of MIS
4. Variance Analysis and coverup plans
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: