Project Planner, Mcnicholas/ Kier, Networkrail CP5 Framework
McNicholas (Kier Group)
Lismirrane Industrial Park, Elstree Road, Elstree, Herts.
WD6 3EA, London, UK
Duties:
Network Rail CP5 Framework:
Developing & maintaining construction programmes using Primavera P6.
Maintaining programme data base and micro planning works scheduled for Rail weekend possessions, identifying & monitoring key milestones and critical path of project.
Liaising with Project Staff, Subcontractors & Clients.
Production of reports for senior management / client against KPI’s.
Performing SPI & Earned Value Analysis.
Analysing delay & disruptions & developing mitigation strategies with project personnel.
Production of Compensation Event / Extension of Time programmes.
Production of Tender Programmes.
Experience working on various NR / NEC forms of contract.
Project experience includes:
Network Rail – CP5 Wessex Feeder Renewals.
LUL Stations Improvement Programme – Electrical works at Baker St Station.
Network Rail – CP5 Wessex Fixed Plant Lighting renewals.
Network Rail – CP5 Wessex New Shorting Circuit Devices (NSCD).
Network Rail – CP5 Wessex Non Traction Renewals (11KV, Transformer, Signalling Power Renewals).
Network Rail – CP5 Wessex Substation Renewals.
Network Rail – CP5 Wessex DC Protection Relays Renewals.