Construction Planner, A.S.G. Scarl, Joint Venture (Aquater – Snamprogetti – Grandi Lavori Fincosit), High-speed line Milan- Bologna

START Date: 
September, 2003
END Date: 
March, 2005

Scope of work:

Designing and building new high-speed line Milan- Bologna, complying with cutting-edge technological standards, as well as being closely integrated with the existing railway network by 8 interconnections. The line extends for 182 km through 42 municipalities, involves the construction of a total of 36 viaducts (some of which will cross existing watercourses), 10 cut-and-cover tunnels, 29 bridges, 65 surveys, almost 200 km of new roads, and the bridge over the Po river (about 400 m long), a cable-stayed bridge, suspended by steel stays from high vertical supporting structures (towers). Client: CEPAV UNO

Activities:

  • Preparing the Level III Schedule/Network called “P.R.G.T. – Programma Generale di Realizzazione della Tratta” (General Line Construction Network)
  • Critical path analysis
  • Change Order Schedule
  • Time-space diagrams analysis for the GA06 tunnel and the Piacenza 1 & 2 viaducts
  • Interference analysis programs
  • Issuing of progress reporting documents and status reports to Client
  • Co-ordination of other specialists’ work on the projects