Senior Project Planner, Mitsubishi Hitachi Power Systems Europe GmbH, Coal Fired Power Plant - Kozienice

START Date: 
June, 2014
END Date: 
March, 2015
  • Lead of international Project Scheduling Team.
  • Development of Project Level 3 Schedule.
  • Implematation of common P6 server solution for all involved parties.