Project Planner, Petrovietnam Engineering, Petronas Refinery and Petrochemical Complex (RAPID)

START Date: 
October, 2016

- Prepare and update project schedule based on the contract.

- Monitor critical activities based on the project schedule and advise construction team.

- Prepares and submit updated work program and cash flow curve showing actual progress and identify areas of weakness and establishes means and methods for recovery, if any, as well as new critical activities.

- Monitor day to day work progress and prepare the weekly and monthly program and report.

- Prepares monthly report reflecting work progress summary.

- Report to the Project Manager about the current work progress and make comparison between plan and actual progress and study impact of alternative approaches to work.