Temporary Works Design, Project Engineer / Senior Engineer / Site Agent, Marine Civil, A variety of tenders and site based projects

START Date: 
April, 1980
END Date: 
April, 1985

 

1980-5                   Site Agent, planning (manual), procurement, formwork and other temporary works design for breakwater extensions, arch bridge, hospital structure, and Syncrolift platform for Marine Civil. Erection of some temporary works.