Summer Placement Student, Morgan Sindall Infrastructure, Taxiway and Cul-De-Sac Reconstruction (£3.1 m)

START Date: 
July, 2013
END Date: 
September, 2013
Designed a Digital Terrain Model for surveying, setting out and automatic grade control to concrete paving.Processed material reconciliations to monitor imports, exports and wastage.Completed site measures to aid project team members.