Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

/ Construction Project Planner / Senior Planner, RUC Cementation Mining, Tanami TE2 Project

START Date: 
September, 2020
END Date: 
May, 2021

Shaft Equip and Headgear project schedule build.

Equip 1400m shaft with 2 Ore skip's and 1 personell skip, plus various piping and power services. 78m headgear with 2 winder buildings. Material handling system with multiple conveyors and transfer towers.

Complete Primavera schedule procure/fabricate, construction & commission fully resourced, built from "Bill Of Quantity" document with reference codes, const accounts and rates. Setup data in such a manner that P6 data is exported to flat file and automatically linked to client progress template. Cost account coding setup for breakdown to sub categories and vendoe references. Activity ID setup with contractor, area and commodity reference. Global coding as per client specifications.

Project setup in cloud enviroment with 2 step authentication access to enable users access from anywhere.

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
50