Senior Engineer Planning, ENGSOL, 220/132/33/22/11kV Substations
START Date:
January, 2019 - Lead planning, scheduling and cost control efforts for all project phases. Maintain and analyze actual and forecasted schedules, cost and risk. Monitor, report and manage deviations.
- Analyzing project requirements with project team, checks that all essential work activities have been identified in enough detail to serve as a basis for developing realistic project schedules.
- Defining, jointly with the project team, project work and cost breakdown structure, develops and maintains properly linked, required resource loaded/integrated, baseline and current schedules that provide time phased baseline, actual and forecast data for project.
- Monitoring project progress and regularly analyzes project critical paths to ensure all critical path activities and project milestones are progressed to the plan, notifies Project Managers of any deviations or scheduling issues, and provides input for optimizing resources.
- Issuing progress reports, program updates and productivity data on a regular basis and as requested by customers and stakeholders.
- Establishing a baseline plan for cost and cash flow performance measurement. Works with project team to define the necessary resources for project completion, evaluating the work breakdown structure and standard productivity.
- Accurately monitoring costs and project cash flow, maintaining detailed estimate to complete and estimate at completion forecast, analyzes variances by using earned value management techniques and advises project management on any cost and cash flow issues arising
- Working closely with engineering, construction, pre-commissioning, commissioning, client and contractors to identify potential changes in scope and quantify the impact of each change in a timely fashion.
- Administering the change order systems and advises the Project Manager on the cost impact of potential changes and ensures the control estimate/budget is current and reflects changes.
- Working with project team to identify and assess the priority of project risks (e.g. schedule, cost and scope risks), maintains the risk register and proposes mitigation plans. Analyzes impact of risk on the overall timeline and costs
- Integrates material resource requirements with project schedule and defines procurement activities and order lead times. Regularly communicates with SCM team and updates schedules to ensure procurement activities take place in a timely way and lead times are optimized to meet schedule targets
Experience Hours (Planning & Scheduling):
1950
Experience Hours (Cost Management):
1950
Experience Hours (Forensic Analysis):
2500 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: