Site Civil engineer, Bombela Civil Joint Venture, Gautrain Rapid Rail Link
START Date:
August, 2006
END Date:
August, 2008 BOMBELA CIVIL JOINT VENTURE: GAUTRAIN PROJECT Viaduct 14 and 15.1: Site Engineer (September 2006 to August 2008)
Site Administration
- Managed and updated Safety inspection procedure’s records
- Controlled Site Documents (submissions of letters to utility authorities, minutes, filing, issuing drawings),
- Managed records of utility progress and issued purchasing orders for site materials
Safety & quality control
- Inspected erected scaffoldings and enforced safety to use or not measures
- Managed and completed First Aider all site compliances ( Completion of the Fem forms during incidents )
- Managed daily records of tower inspections and shutter access for the Piers (structures)
- Managed subcontractors compliances to safety and environmental regulations
- Arranged safety inductions for subcontractors before commencement of work
- Managed procuring of drainage pipes orders, inspected the quality delivered against issued for construction drawings and updated piping schedule
- Inspected and managed reinforcement delivered on site according to bending schedule
- Updated and kept records of dates of concrete cast
- Coordinated sending cubes to Midrand lab
Site inspection
- Managed and structured subcontractors for site establishment, fencing and clearing
- Supervised of platform treatment for all weather conditions
- Evaluated the quality of work done for payment
- Accepted and checked materials delivered on site
- Managed and coordinated compliances of environmental regulations
- Compiled and updated monthly reports of accidents, water management, noise measurements etc.
- Authored and updated 3 months construction program and 3 weekly forecast program
- Monitored site work interphase construction work per section and monitored progress
- Monitored, managed and authorised access for sub- contractors per section of work
- Supervised piling works that is reinforcement casing, pile depth and concrete slump before casting.
- Supervised lateral support work that is reinforcement casing, pile depth and concrete sump before casting.
- Managed, inspected and supervised road works that is stabilization of road work, resealing of road and fill of potholes.
- Monitored fencing sub-contractor and validated completion of work
- Identified, verified and monitored tree felling contractors for parking
- Prepared and updated progress reports including progress picture
Contracts
- Evaluated and verified schedule of quantities submitted by contractors
- Estimated cost for material and equipment for construction
- Issued and validated of completion certificates, measurements of the completed works (area & volumes) for As – built drawing
- Verified payment certificates ( re-measurements on work done)
- Evaluated Pre- tender documents, Participated in the preparation of the overall work programme and balanced resources to complete in time,
- Estimated cost of temporary and permanent works, tender inspections and adjudication and prepared back charges schedules for the client
Results:
- Completed of Viaduct 14 and 15.1 Site Establishment, Piling works, Relocation of exciting Utilities.