Planner, Birse Metro, Step Free Access
START Date:
December, 2008
END Date:
June, 2009 Birse Metro Step Free Access (Bank of four) London Underground December 2008 to June 2009 (Planning software P6)
Working to provide Step Free Access to four London Underground sites (Greenford, West Kensington, Newbury Park, Amersham) (Planning software P6)
Initially working on two programmes covering installation of Lifts stairs and bridge at Amersham & Newbury Park
Working under an NEC contract to London Underground. Period submission inline with contract ensuring successful submission and acceptance of contractors programmes
Cost loading of programme inline with CBS and agreed changes to contract